Gulfkeystone Production Facility PF1 to RETM 16″ Pipeline

Date: 1/11/2018 – 1/8/2019

Location

Duhok-Shekhan

Scope of Work

Gulfkeystone Production Facility PF1 to RETM 16″ Pipeline

Work Size

13 Km  16″ Pipeline, ROW,Stringing,Bending,Welding, Blasting & Coating,Trenching,Bedding, Lowering in, Padding, FOCC & FOC, Backfill, Riprap,HDD Crossing, Creek crossing, Tie in, Marker.

Job Summary

  • Procurement and Construction Contract

  • Complete planning,Project Management,Excellence Execution.

  • Preparing Project Documenations such As built Drawings,Inspection Reports, Method Statement, Certificates and Calibrations, Surevy Reports.

  • Coordination and supervision.

  • Quality Control Department provide quality control engineer per each activity.

  • Compelete Civil work execution according Specifications,Approved typical drawings and International standard.

  • Perform Hydrostatic test for the Pipeline.