Kurdistan Pump Station 2

Date: 1/2/2018 – 1/10/2018

Location

Dohuk – Shekhan

Scope of Work

Prefabrication, Fabrication, Welding, Valve Installation, Flange management, underground piping installation, Support Installation, Coating, Piping Blasting and Painting, Inert Gas System Painting

Work Size

12,500 Dia-inch

Job Summary

  • Complete planning, Project Management, Excellence Execution.

  • Coordination and supervision.

  • Providing Quality assurance service to gain ultimate quality and productivity.

  • Piping Fabrication as per ASME B31.3, Welder qualification as perĀ  API 1104 and Flange management as per ASME PCC-1 and ASME B31.3.

  • Performing Full Blasting,Coating & Painting as per ISO 12944-4 ISO 12944-5 ISO 12944-7 ISO 1461 ISO 21809-1 ISO 4624 ISO 8503-2 &SSPC-PA2.

  • HSE Plan & Supervision as per IMS ISO 45001